The project scope statement defines boundaries; which option describes this?

A description of the project scope

Defining what is included and excluded from a project, i.e., its boundaries, is the purpose of the project scope statement. It documents the project scope, the deliverables, the acceptance criteria, constraints, and assumptions, and explicitly states what is in scope and what is out of scope. This clarity helps prevent scope creep and guides planning and execution.

A project budget deals with costs, a risk register tracks potential risks and responses, and a communication plan outlines how information is shared with stakeholders. These are important artifacts, but they describe different aspects of project management and do not define the boundaries of what the project will and will not do.

A project budget

A risk register

A communication plan